City of Chicago

Procurement Services

We are the contracting authority for the procurement of goods and services for the City of Chicago

contract.detail.title

Contract Details

   View payment details

Original Contract

DUR in the Award Amount column means that the contract award total Depends Upon Requirements. A Depends Upon Requirements contract is an indefinite quantities contract in which the city places orders as needed. The vendor is not guaranteed any particular contract award amount.
Contract (PO) # Disclosure # Award Date Start Date End Date Original Award Amount
02/11/2020 $6,710,206.90

Modifications/Amendments

Modification # Description Disclosure # Award Date Start Date End Date Amount
1162911
CONCOURSE B, C AND TAXIWAY Y PAVEMENT RECONSTRUCTION 09/08/2020 $13,663.27
11629110
CONCOURSE B, C AND TAXIWAY Y PAVEMENT RECONSTRUCTION 09/09/2021 $266,000.00
CONCOURSE B, C AND TAXIWAY Y PAVEMENT RECONSTRUCTION 02/15/2022 $54,250.00
CONCOURSE B, C AND TAXIWAY Y PAVEMENT RECONSTRUCTION 03/08/2022 $6,354.59
11629113
CONCOURSE B, C AND TAXIWAY Y PAVEMENT RECONSTRUCTION 04/19/2022 ($162,707.35)
CONCOURSE B, C AND TAXIWAY Y PAVEMENT RECONSTRUCTION 05/12/2022 $68,000.00
CONCOURSE B, C AND TAXIWAY Y PAVEMENT RECONSTRUCTION 05/20/2022 ($54,893.93)
1162913
CONCOURSE B, C AND TAXIWAY Y PAVEMENT RECONSTRUCTION 09/17/2020 $81,878.12
1162914
CONCOURSE B, C AND TAXIWAY Y PAVEMENT RECONSTRUCTION 11/19/2020 $0.00
1162915
CONCOURSE B, C AND TAXIWAY Y PAVEMENT RECONSTRUCTION 12/22/2020 ($40,957.20)
1162916
CONCOURSE B, C AND TAXIWAY Y PAVEMENT RECONSTRUCTION 02/18/2021 $50,625.05
1162917
CONCOURSE B, C AND TAXIWAY Y PAVEMENT RECONSTRUCTION 02/25/2021 ($19,665.75)
1162918
CONCOURSE B, C AND TAXIWAY Y PAVEMENT RECONSTRUCTION 08/26/2021 ($560,405.00)
1162919
CONCOURSE B, C AND TAXIWAY Y PAVEMENT RECONSTRUCTION 09/08/2021 $24,267.00