DUR in the Award Amount column means that the contract award total Depends Upon Requirements. A Depends Upon Requirements contract is an indefinite quantities contract in which the city places orders as needed. The vendor is not guaranteed any particular contract award amount.
Contract (PO) # Disclosure # Award Date Start Date End Date Original Award Amount
02/08/2012 $6,679,896.40

Modifications/Amendments

Modification # Description Disclosure # Award Date Start Date End Date Amount
261281
2010 Residential Sound Insulation Program Midway - Bid Pkg# 4 (350 Homes),Spec# 100406, Req# 62897, RFQ# 3817 08/30/2012 $665,679.29
261282
2010 Residential Sound Insulation Program Midway - Bid Pkg# 4 (350 Homes),Spec# 100406, Req# 62897, RFQ# 3817 07/16/2013 ($76,795.83)
2010 Residential Sound Insulation Program Midway - Bid Pkg# 4 (350 Homes),Spec# 100406, Req# 62897, RFQ# 3817 02/04/2014 $11,103.88
2010 Residential Sound Insulation Program Midway - Bid Pkg# 4 (350 Homes),Spec# 100406, Req# 62897, RFQ# 3817 04/24/2014 $2,565.10
261285
2010 Residential Sound Insulation Program Midway - Bid Pkg# 4 (350 Homes),Spec# 100406, Req# 62897, RFQ# 3817 07/16/2014 ($3,125.13)