Contract (PO) # Disclosure # Award Date Start Date End Date Original Award Amount
08/20/2012 08/20/2012 08/19/2015 Up To $27,634,300.00

Modifications/Amendments

Modification # Description Disclosure # Award Date Start Date End Date Amount
266591
GROUP A) AIRSIDE CONCRETE MAINTENANCE AT O'HARE & MIDWAY, SHOTCRETE (LANDSIDE & AIRSIDE) AT O'HARE & MIDWAY, AND RAMP REPLACEMENT AT MIDWAY; AND GROUP B) RAMP REPLACEMENT AT O'HARE 06/11/2014 08/20/2012 08/19/2015 $12,400,000.00
GROUP A) AIRSIDE CONCRETE MAINTENANCE AT O'HARE & MIDWAY, SHOTCRETE (LANDSIDE & AIRSIDE) AT O'HARE & MIDWAY, AND RAMP REPLACEMENT AT MIDWAY; AND GROUP B) RAMP REPLACEMENT AT O'HARE 04/09/2018 08/20/2012 04/30/2019 $2,650,000.00
GROUP A) AIRSIDE CONCRETE MAINTENANCE AT O'HARE & MIDWAY, SHOTCRETE (LANDSIDE & AIRSIDE) AT O'HARE & MIDWAY, AND RAMP REPLACEMENT AT MIDWAY; AND GROUP B) RAMP REPLACEMENT AT O'HARE 09/10/2018 08/20/2012 04/30/2019 $2,362,101.30
GROUP A) AIRSIDE CONCRETE MAINTENANCE AT O'HARE & MIDWAY, SHOTCRETE (LANDSIDE & AIRSIDE) AT O'HARE & MIDWAY, AND RAMP REPLACEMENT AT MIDWAY; AND GROUP B) RAMP REPLACEMENT AT O'HARE 04/26/2019 08/20/2012 07/31/2019 DUR
GROUP A) AIRSIDE CONCRETE MAINTENANCE AT O'HARE & MIDWAY, SHOTCRETE (LANDSIDE & AIRSIDE) AT O'HARE & MIDWAY, AND RAMP REPLACEMENT AT MIDWAY; AND GROUP B) RAMP REPLACEMENT AT O'HARE 08/10/2015 08/20/2012 02/18/2016 $6,966,361.76
266594
GROUP A) AIRSIDE CONCRETE MAINTENANCE AT O'HARE & MIDWAY, SHOTCRETE (LANDSIDE & AIRSIDE) AT O'HARE & MIDWAY, AND RAMP REPLACEMENT AT MIDWAY; AND GROUP B) RAMP REPLACEMENT AT O'HARE 02/16/2016 08/20/2012 08/19/2016 DUR
GROUP A) AIRSIDE CONCRETE MAINTENANCE AT O'HARE & MIDWAY, SHOTCRETE (LANDSIDE & AIRSIDE) AT O'HARE & MIDWAY, AND RAMP REPLACEMENT AT MIDWAY; AND GROUP B) RAMP REPLACEMENT AT O'HARE 08/04/2016 08/20/2012 02/16/2017 $4,750,000.00
266597
GROUP A) AIRSIDE CONCRETE MAINTENANCE AT O'HARE & MIDWAY, SHOTCRETE (LANDSIDE & AIRSIDE) AT O'HARE & MIDWAY, AND RAMP REPLACEMENT AT MIDWAY; AND GROUP B) RAMP REPLACEMENT AT O'HARE 02/17/2017 08/20/2012 10/31/2017 DUR
GROUP A) AIRSIDE CONCRETE MAINTENANCE AT O'HARE & MIDWAY, SHOTCRETE (LANDSIDE & AIRSIDE) AT O'HARE & MIDWAY, AND RAMP REPLACEMENT AT MIDWAY; AND GROUP B) RAMP REPLACEMENT AT O'HARE 05/03/2017 08/20/2012 10/31/2017 $9,116,411.99
GROUP A) AIRSIDE CONCRETE MAINTENANCE AT O'HARE & MIDWAY, SHOTCRETE (LANDSIDE & AIRSIDE) AT O'HARE & MIDWAY, AND RAMP REPLACEMENT AT MIDWAY; AND GROUP B) RAMP REPLACEMENT AT O'HARE 10/27/2017 08/20/2012 04/30/2018 DUR