Contract (PO) # Disclosure # Award Date Start Date End Date Original Award Amount
07/22/2015 07/27/2015 10/27/2027 Up To $62,306,440.00

Modifications/Amendments

Modification # Description Disclosure # Award Date Start Date End Date Amount
Replacement of Chillers 1-5 and Upgrade of South Cooling Tower - ORD, Spec. 126044 05/10/2016 07/27/2015 10/27/2027 $449,550.00
Replacement of Chillers 1-5 and Upgrade of South Cooling Tower - ORD, Spec. 126044 09/12/2017 07/27/2015 10/27/2027 $572,274.10
Replacement of Chillers 1-5 and Upgrade of South Cooling Tower - ORD, Spec. 126044 11/19/2018 07/27/2015 10/27/2027 $924,271.70
Replacement of Chillers 1-5 and Upgrade of South Cooling Tower - ORD, Spec. 126044 09/23/2019 07/27/2015 10/27/2027 ($457,351.59)
328356
Replacement of Chillers 1-5 and Upgrade of South Cooling Tower - ORD, Spec. 126044 02/03/2021 07/27/2015 10/27/2027 $155,400.00
Replacement of Chillers 1-5 and Upgrade of South Cooling Tower - ORD, Spec. 126044 08/05/2022 07/27/2015 10/27/2027 $135,000.00
328358
Replacement of Chillers 1-5 and Upgrade of South Cooling Tower - ORD, Spec. 126044 12/19/2022 07/27/2015 10/27/2027 $55,000.00
Replacement of Chillers 1-5 and Upgrade of South Cooling Tower - ORD, Spec. 126044 04/10/2024 07/27/2015 10/27/2027 $57,753.42