Original Contract

DUR in the Award Amount column means that the contract award total Depends Upon Requirements. A Depends Upon Requirements contract is an indefinite quantities contract in which the city places orders as needed. The vendor is not guaranteed any particular contract award amount.
Contract (PO) # Disclosure # Award Date Start Date End Date Original Award Amount
03/02/2016 $2,516,345.00

Modifications/Amendments

Modification # Description Disclosure # Award Date Start Date End Date Amount
339581
AMC Access Road Pavement Reconstruction - ORD, Spec 133688, H6195.15-00 10/26/2016 ($134,330.00)
3395810
AMC Access Road Pavement Reconstruction - ORD, Spec 133688, H6195.15-00 11/22/2023 ($3,428.05)
339582
AMC Access Road Pavement Reconstruction - ORD, Spec 133688, H6195.15-00 10/28/2016 $405,082.90
AMC Access Road Pavement Reconstruction - ORD, Spec 133688, H6195.15-00 12/03/2016 $54,715.50
339584
AMC Access Road Pavement Reconstruction - ORD, Spec 133688, H6195.15-00 12/05/2016 $6,703.52
AMC Access Road Pavement Reconstruction - ORD, Spec 133688, H6195.15-00 12/06/2016 ($12,600.00)
AMC Access Road Pavement Reconstruction - ORD, Spec 133688, H6195.15-00 02/15/2017 $37,124.10
AMC Access Road Pavement Reconstruction - ORD, Spec 133688, H6195.15-00 02/16/2017 ($35,000.00)
339588
AMC Access Road Pavement Reconstruction - ORD, Spec 133688, H6195.15-00 03/01/2017 ($44,897.55)
339589
AMC Access Road Pavement Reconstruction - ORD, Spec 133688, H6195.15-00 04/11/2017 ($8,006.36)