City of Chicago
contract.detail.title

Contract Details

   View payment details

Original Contract

DUR in the Award Amount column means that the contract award total Depends Upon Requirements. A Depends Upon Requirements contract is an indefinite quantities contract in which the city places orders as needed. The vendor is not guaranteed any particular contract award amount.
Contract (PO) # Disclosure # Award Date Start Date End Date Original Award Amount
07/13/2016 $19,553,707.90

Modifications/Amendments

Modification # Description Disclosure # Award Date Start Date End Date Amount
419441
Runway 4R-22L Rehabilitation - MDW, Spec 143520 11/04/2016 $157,630.00
Runway 4R-22L Rehabilitation - MDW, Spec 143520 01/19/2017 $40,000.00
Runway 4R-22L Rehabilitation - MDW, Spec 143520 01/30/2017 $59,386.16
Runway 4R-22L Rehabilitation - MDW, Spec 143520 01/31/2017 $43,800.00
Runway 4R-22L Rehabilitation - MDW, Spec 143520 02/01/2017 $12,720.59
Runway 4R-22L Rehabilitation - MDW, Spec 143520 05/26/2017 $59,601.78
Runway 4R-22L Rehabilitation - MDW, Spec 143520 05/30/2017 $14,760.82
4194417
Runway 4R-22L Rehabilitation - MDW, Spec 143520 06/06/2017 ($1,037,607.26)
Runway 4R-22L Rehabilitation - MDW, Spec 143520 06/07/2017 $86,217.11
Runway 4R-22L Rehabilitation - MDW, Spec 143520 06/08/2017 ($100,000.00)
419442
Runway 4R-22L Rehabilitation - MDW, Spec 143520 11/08/2016 ($1,259,103.00)
4194420
Runway 4R-22L Rehabilitation - MDW, Spec 143520 06/16/2017 $97,035.00
Runway 4R-22L Rehabilitation - MDW, Spec 143520 07/05/2017 $814,267.54
Runway 4R-22L Rehabilitation - MDW, Spec 143520 11/16/2017 $9,982.52
4194423
Runway 4R-22L Rehabilitation - MDW, Spec 143520 12/01/2017 ($1,345,930.83)
4194424
Runway 4R-22L Rehabilitation - MDW, Spec 143520 07/06/2018 $574,369.83
Runway 4R-22L Rehabilitation - MDW, Spec 143520 09/19/2018 ($91,308.03)
Runway 4R-22L Rehabilitation - MDW, Spec 143520 01/30/2019 $67,329.18
Runway 4R-22L Rehabilitation - MDW, Spec 143520 04/26/2019 $275,000.00
4194428
Runway 4R-22L Rehabilitation - MDW, Spec 143520 05/10/2019 ($35,230.00)
Runway 4R-22L Rehabilitation - MDW, Spec 143520 11/10/2016 $111,121.96
419445
Runway 4R-22L Rehabilitation - MDW, Spec 143520 12/06/2016 $157,500.00
419446
Runway 4R-22L Rehabilitation - MDW, Spec 143520 12/08/2016 ($192,925.00)
419447
Runway 4R-22L Rehabilitation - MDW, Spec 143520 12/29/2016 $130,000.00
419448
Runway 4R-22L Rehabilitation - MDW, Spec 143520 12/30/2016 $54,000.00